Click on the image to view the building
process |
moladi
construction process
- Position raft
foundation former
- Dig Foundation
trenches
- Place underlay and
reinforcing according to Engineer design and cast dense concrete
- Power float slab
- Erect
moladi
plastic shutter formwork
- Place plumbing and
electrical pipes-window and door frames - reinforcing - roof truss
blockouts - 4 hours.
- Fill
moladi
formwork with mortar (concrete without stone), either by bucket or
pump - 2 hours
- Remove the
moladi
formwork the following day.
- Fix Ceiling, roof,
electrical wiring, paint glaze, etc.
- Complete
|
|